We wish to advise that work continues to progress well.
Please see the construction update below:
Works planned on site for the next 6 months
Site Possession – 01 September 2022 | Anticipated Project Completion – Early 2025
Estimated timeframe: 30 month single stage development
Site Establishment
- Site Accommodation and Setup
 - Hoardings and Fences
 - Disconnection of Services
 - Temporary construction power and water
 - Tree protection
 
Services Infrastructure
- Stormwater upgrade on Horsley Avenue
 - Power upgrade to site
 
Demolition
- Removal of all items that need to salvaged from the club to be reimagined in the new development
 - Demolition of Club Willoughby buildings
 - Site clearing
 
Shoring
- Preparation of piling platform
 - Piling around the perimeter of the site
 
Excavation
- Bulk Excavation
 