Estimated Construction Completion: Q4 2024
Estimated Settlement: Q1 2025
Click here to view Audrey St.Leonards construction timeline and 360-degree views.
We wish to advise that building work continues to progress well.
Please see the construction update for the past quarter below:
Milestones:
- Detailed Excavation of future East-West Link Completed
- Approx. 17,000 m3 of soil removed off site
- Crane Base has been poured
Works planned on site for the next quarter of 2023:
- Completion of Bulk Excavation
- Installation of Tower Crane
- Detailed Excavation to commence for lift pits and pad footings
- Establishment and commencement of structural and inground services trades
- Commence undergrounding of Overhead Powerlines along Canberra Avenue
![](https://b2299988.smushcdn.com/2299988/wp-content/uploads/2023/07/Audrey-Hero-230718-2-1024x576.jpg?lossy=1&strip=1&webp=1)
Programme
The key programme items are as follows:
- Site set up works – Completed
- Bulk excavation – In Progress
- Basement works – Not started
- Structure works – Not started
- Services rough in – Not started
- Window glazing – Not started
- Facade cladding – Not started
- Internal fit out works – Not started
- Finishing works – Not started
- Landscaping – Not started
- Title registration – Not started
- Ready to settle –