Construction Update – Audrey

November 2025

Estimated Construction Completion: Q1 2026
Estimated Settlement: Q1 2026

We wish to advise that building work continues to progress well. Please see the construction update below:

Milestones:

Works completed from previous quarter
(August – October 2025):

  • External framing and installation of window and door sub jambs, subheads and sub sills up to and including Level 17 — to be completed
  • External cladding and façade works from L4 – L17 — to be completed
  • Scaffolding to be dropped down to L4
  • Builder lift to be operation
  • Removal of hoist
  • Removal of loading bays
  • Prepare for removal of tower crane
  • Internal hebel walls and framing to all levels and units – to be completed
  • Waterproofing up to and including L17 — to be completed
  • Tiling to wet areas, up to and including L17 — to be completed
  • Kitchens / wardrobes up to and including L15 — to be completed
  • Internal fitout up to and including L15 — to be completed
  • Commencement of builders clean
  • Carpark preparation and fitout B4, B3, B2 — to be completed
  • Commencement carpark painting B4, B3, B2 — to be completed
  • Commencement of mains water upgrade — to be completed
  • Power energisation and commission — to be completed
  • Commencement landscaping – internal and to East–West Link
  • Commencement of civil works to council domain

Works planned on site for the next quarter
(November – January 2026):

  • Removal of scaffolding
  • Removal of tower crane
  • Completion of façade works
  • Completion of balustrades
  • Completion of all tiling to balconies
  • All apartments completed internally
  • All corridors completed
  • Carpark fitout completed
  • Permanent power energisation and commissioning completed
  • Mains water upgrade completed and connected to site
  • Gas connection to site completed
  • NBN connection to site completed
  • Public domain works commenced and ongoing
  • East–West Link works commenced and ongoing
  • Commencement of all amenities and common areas
  • Lifts fitted off
  • Commencement oof Penthouses and ongoing

Programme

The key programme items are as follows:

  1. Site set up works — Completed
  2. Bulk excavation — Completed
  3. Basement works — In-Progress
  4. Structure works — Completed
  5. Services rough in — Completed
  6. Window glazing — Completed
  7. Facade cladding — In-Progress
  8. Internal fit out works — In-Progress
  9. Finishing works — In-Progress
  10. Landscaping — In-Progress
  11. Title registration — In-Progress
  12. Ready to settle —

Next Update: February 2026