Estimated Construction Completion: Q1 2026
Estimated Settlement: Q1 2026
We wish to advise that building work continues to progress well. Please see the construction update below:
Milestones:
Works completed from previous quarter
(August – October 2025):
- External framing and installation of window and door sub jambs, subheads and sub sills up to and including Level 17 — to be completed
- External cladding and façade works from L4 – L17 — to be completed
- Scaffolding to be dropped down to L4
- Builder lift to be operation
- Removal of hoist
- Removal of loading bays
- Prepare for removal of tower crane
- Internal hebel walls and framing to all levels and units – to be completed
- Waterproofing up to and including L17 — to be completed
- Tiling to wet areas, up to and including L17 — to be completed
- Kitchens / wardrobes up to and including L15 — to be completed
- Internal fitout up to and including L15 — to be completed
- Commencement of builders clean
- Carpark preparation and fitout B4, B3, B2 — to be completed
- Commencement carpark painting B4, B3, B2 — to be completed
- Commencement of mains water upgrade — to be completed
- Power energisation and commission — to be completed
- Commencement landscaping – internal and to East–West Link
- Commencement of civil works to council domain
Works planned on site for the next quarter
(November – January 2026):
- Removal of scaffolding
- Removal of tower crane
- Completion of façade works
- Completion of balustrades
- Completion of all tiling to balconies
- All apartments completed internally
- All corridors completed
- Carpark fitout completed
- Permanent power energisation and commissioning completed
- Mains water upgrade completed and connected to site
- Gas connection to site completed
- NBN connection to site completed
- Public domain works commenced and ongoing
- East–West Link works commenced and ongoing
- Commencement of all amenities and common areas
- Lifts fitted off
- Commencement oof Penthouses and ongoing
Programme
The key programme items are as follows:
- Site set up works — Completed
- Bulk excavation — Completed
- Basement works — In-Progress
- Structure works — Completed
- Services rough in — Completed
- Window glazing — Completed
- Facade cladding — In-Progress
- Internal fit out works — In-Progress
- Finishing works — In-Progress
- Landscaping — In-Progress
- Title registration — In-Progress
- Ready to settle —
Next Update: February 2026