Estimated Construction Completion: Q4 2025
Estimated Settlement: Q4 2025
Click here to view a timeline of the build go to our 360 photo captured in August 2025
We wish to advise that building work continues to progress well. Please see the construction update below:
Milestones:
Works completed from previous quarter
(April – June 2025):
- Structure – Complete
- External framing and Installation of window and door sub jambs, subheads and sub sills up to and including L15 – Complete
- External Cladding – Subframing in preparation for cladding installation, L4-L17 – Complete
- Internal hebel walls and framing – up to and including L15 – Complete
- Services rough up to and including L15 – Complete
- Waterproofing up to and including L12 – Complete
- Tiling to Wet areas, up to and including L8 – Complete
- Kitchens / Wardrobes – up to and including L8 installed
- Commencement of services fitout
- Commencement of Carpark preparation and Fitout
- Commencement carpark painting
- Commencement of Mains Water Upgrade

Works planned on site for the next quarter
(July – September) of 2025:
- External framing and Installation of window and door sub jambs, subheads and sub sills up to and including Level 17 – To be completed
- External Cladding and Façade Works – from L4-L17 – To be Completed
- Scaffolding to be dropped down to L4
- Builder Lift to be operation
- Removal of Hoist
- Removal of Loading Bays
- Prepare for removal of Tower Crane
- Internal Hebel walls and framing – to all levels and units – To be Completed
- Waterproofing up to and including L17 – To be completed
- Tiling to Wet areas, up to and including L17 – To be completed
- Kitchens / Wardrobes – up to and including L15 – To be completed
- Internal Fitout – up to and including L15 to be completed
- Commencement of Builders Clean
- Carpark preparation and Fitout – B4, B3, B2 to be completed
- Commencement carpark painting – B4, B3, B2 to be completed
- Commencement of Mains Water Upgrade – to be completed
- Power Energisation & Commission to be completed
- Commencement Landscaping – Internal and to East West Link
- Commencement of Civil Works to Council Domain

Programme
The key programme items are as follows:
- Site set up works — Completed
- Bulk excavation — Completed
- Basement works — In-Progress
- Structure works — Completed
- Services rough in — In-Progress
- Window glazing — In-Progress
- Facade cladding — In-Progress
- Internal fit out works — In-Progress
- Finishing works — In-Progress
- Landscaping — In-Progress
- Title registration — In-Progress
- Ready to settle —

Next Update: April 2025