Construction Update – Audrey

August 2025

Estimated Construction Completion: Q4 2025
Estimated Settlement: Q4 2025

Click here to view a timeline of the build go to our 360 photo captured in August 2025

We wish to advise that building work continues to progress well. Please see the construction update below:

Milestones:

Works completed from previous quarter
(April – June 2025):

  • Structure – Complete
  • External framing and Installation of window and door sub jambs, subheads and sub sills up to and including L15 –  Complete
  • External Cladding – Subframing in preparation for cladding installation, L4-L17 – Complete
  • Internal hebel walls and framing – up to and including L15 – Complete
  • Services rough up to and including L15 – Complete
  • Waterproofing up to and including L12 – Complete
  • Tiling to Wet areas, up to and including L8 – Complete
  • Kitchens / Wardrobes – up to and including L8 installed
  • Commencement of services fitout
  • Commencement of Carpark preparation and Fitout
  • Commencement carpark painting
  • Commencement of Mains Water Upgrade

Works planned on site for the next quarter
(July – September) of 2025:

  • External framing and Installation of window and door sub jambs, subheads and sub sills up to and including Level 17 – To be completed
  • External Cladding and Façade Works – from L4-L17 – To be Completed
  • Scaffolding to be dropped down to L4
  • Builder Lift to be operation
  • Removal of Hoist
  • Removal of Loading Bays
  • Prepare for removal of Tower Crane
  • Internal Hebel walls and framing – to all levels and units – To be Completed
  • Waterproofing up to and including L17 – To be completed
  • Tiling to Wet areas, up to and including L17 – To be completed
  • Kitchens / Wardrobes – up to and including L15 – To be completed
  • Internal Fitout – up to and including L15 to be completed
  • Commencement of Builders Clean
  • Carpark preparation and Fitout – B4, B3, B2 to be completed
  • Commencement carpark painting – B4, B3, B2 to be completed
  • Commencement of Mains Water Upgrade – to be completed
  • Power Energisation & Commission to be completed
  • Commencement Landscaping – Internal and to East West Link
  • Commencement of Civil Works to Council Domain

Programme

The key programme items are as follows:

  1. Site set up works — Completed
  2. Bulk excavation — Completed
  3. Basement works — In-Progress
  4. Structure works — Completed
  5. Services rough in — In-Progress
  6. Window glazing — In-Progress
  7. Facade cladding — In-Progress
  8. Internal fit out works — In-Progress
  9. Finishing works — In-Progress
  10. Landscaping — In-Progress
  11. Title registration — In-Progress
  12. Ready to settle —

Next Update: April 2025