Construction Update – Elena

22.06.2021

Elena continues to hit its milestones: 

Milestones: 

-Render and architectural details to the façade are 60% complete with scaffolding being removed on the northern façade. Due to remove all scaffolding by early July. 

-Permanent power with the substation now live. 

-We are preparing install storages cages in the basement. 

-Internal fit out of the apartments is progressing well with front doors installed to level 1 units and only minor fittings still to be installed. 

-Initial clean has commenced. 

-All windows and glazing have been installed. 

-Stage 1 of the new cul-de-sac works has been completed. 

-Commencement of sites stormwater works and preparing for civil works.

Works planned on site for the next quarter of 2021: 

-Completion of civil works 

-Completion of internal fit out 

-Completion of podium landscape/pool and common areas 

-Completion of façade works

Click the link below for more info and to view our construction timeline and 360 degree views.

https://hyecorp.sites.firstvue.com.au/elena-42db/fv-timeline/